2/28/2017 - PHASE I ROAD RESTORATION PROJECT
Phase 1 of the Road Restoration Project will likely begin this Spring in the “Web Area” of town that are defined by High Street and its adjacent roads. This restoration project will reconstruct those roads as well as the storm water sewer system beneath them. We have bid out this project and received very favorable numbers that have come in below that which was projected by our engineers. Contract has been awarded to Tobacco & Sons of Bristol Ct. for the sum of $ 2,455,000 and a Notice to Proceed has been issued. Some preliminary work will begin week of April 24 with actual construction scheduled to begin May 8th with a projected completion date of October 14th.